Unlock direct contact details for up to 10 lawyers so you can call or WhatsApp the right legal professional and move your matter forward with confidence.
Civil Petition for Leave to Appeal No. 915 of 1983, decided on 2nd July, 1986.
(On appeal from the judgment and order of the Lahore High Court, dated 11‑5‑1983 in F.A.O. 1011 of 1983).
‑‑‑Art. 185(3)‑‑Leave to appeal, grant of‑‑Petitioner reiterating all grounds of objections raised in Court of first instance regarding arbitrators' findings‑‑Matter having been considered by Trial Court as well as by First: Appellate Court and both Courts coming to correct conclusion regarding question involved in petition‑‑Petition being devoid of merits, dismissed.
Kh. Ahmad Tariq Rahim, Advocate Supreme Court and Kh. Mushtaq Ahmad, Advocate‑on‑Record (absent) for Petitioner.
Raja Muhammad Akram, Advocate Supreme Court and M.Z. Khalil, Advocate‑on‑Record (absent) for Respondent.
Date of hearing: 2nd July, 1986.
According to the petitioner it is a limited Company registered under the Companies Act, engaged in the construction work as Contractors and Mr. Shoaib is the Managing Director of the petitioner‑Company.
2. Respondent National Bank of Pakistan issued a notice for pre -qualification of Contractors for the construction of its building in Civil Lines, Gujranwala. The petitioner, along with other contractors, submitted details asked for in this connection. Their pre‑qualification was accepted and accordingly tender documents were issued to them. After the acceptance of the tender of the petitioner‑Company they were informed vide letter No. Eng/HO/83/1675, dated 9‑4‑1981 and an agreement regarding the work was concluded wherein it was stipulated that the building was to be completed within a period of 18 months and payment of 10 of the estimated cost as mobilization advance, against bank guarantee to be furnished by the petitioner‑Company.
3. Later on there arose some differences between the petitioner Company and the respondent‑Bank which subsequently developed into a dispute precisely to say that the agreement for construction of the building between the petitioner and respondent was executed with regard to the work relating to one unit. According to the petitioner, there was no indication in the Contract that the construction work was to be done in phases. Had this been the position the period for each phase would have been specified. The petitioner‑Company submitted construction schedule spreading over the period of construction not only along with the tender but also on the date of opening of the tenders but no objection was raised by the respondent‑Bank.
4. The matter was referred to the Arbitrator who, vide his award, dated 23‑9‑1982 rejected the claim of the petitioner. Petitioner, aggrieved from the said 'award, filed objection petition before the Senior Civil Judge, Lahore who per order, dated 20‑2‑1983 gave the following finding:
"Anyhow the objector's contentions are also considered. The objector has mainly confined to certain matters which are purely question of facts and which can only be decided and adjudicated upon by the arbitrator himself. The Court cannot, therefore, in such matters and what objector has stated in the grounds mentioned in the objection petition, do not constitute by any stretch of imagination, to be misconduct on the part of the arbitrator or to hold that the arbitrator has miss conducted the proceedings."
Accordingly, the learned Senior Civil Judge dismissed the objection petition filed by the petitioner and made the award, dated 23‑9‑1982 Rule of the Court vide his judgment, dated 20‑2‑1983. The learned High Court Judge after summoning the record of the proceedings before the arbitrator held as follows:‑‑
"The contention of the learned counsel for the appellant that the evidence of various witnesses had been incorrectly reproduced by the arbitrator in his award was not found to be correct on verification with the original record. The arbitrator after receiving and examining the evidence of the parties, reached the conclusion that drawings, etc. for constructing the building in two phases were given to the appellant which was bound to carry out the construction in two phases. The finding of the arbitrator is not shown to be based on any misreading or misinterpretation of evidence produced before him. The grievance of the learned counsel for the appellant that the learned trial Court did not frame issues and did not give opportunity to the appellant to lead evidence in support of its objections, is without force because as the perusal of the record shows the appellant never pressed for the framing of issues nor for adducing evidence, its counsel simply addressed arguments without any demur "
Learned counsel for the petitioner reiterated all the grounds of objection raised in the Court of first instance regarding arbitrator's findings. Suffice to say that there is no force in the contentions raised by the learned counsel before us. The matter has been considered by the learned trial Court as well as by the first appellate Court and both the Courts have come to the correct conclusion regarding the question involved in the petition. We find no merit in this petition which is, accordingly, dismissed.
M.I. Petition dismissed.
Dealing with a matter like this? Connect with a verified advocate in your city — free on SJP Lawyers Directory.
🔍 Find a Lawyer